Issue - meetings
Westover Urgent Works - Milford-On-Sea and Next Steps - Update Report
Meeting: 07/07/2021 - Cabinet (Item 10)
10 Westover Urgent Works - Milford-On-Sea - Update Report PDF 1 MB
Minutes:
RESOLVED:
That the completion of the urgent works and the latest expected financial contribution required from the Council (subject to successful confirmation and receipt of third-party funding), be noted.
REASONS FOR DECISION:
As set out in the report.
KEY DECISION:
No.
PORTFOLIO:
Environment and Coastal Services.
ALTERNATIVE OPTIONS CONSIDERED/REJECTED:
As set out in the report.
DECLARATIONS OF INTEREST(S):
None.
DISCUSSION:
The Portfolio Holder introduced the report and welcomed the achievement of completing the emergency works during a challenging year. Looking forward, the Council was working closely with Bournemouth, Christchurch and Poole Council in the development of a Christchurch Bay Strategy, covering the entire coastline from Hengistbury Head to Hurst Spit.
The Portfolio Holder for Finance highlighted the strong financial position of the Council’s reserves which enabled the response during 2020. Whilst it was hoped that several funding areas would bring the final cost to the Council down, it was still anticipated that the Council’s contribution would be in excess of £500k, which was not sustainable for a District Council. Looking forward, these type of projects would need to secure significant external funding.