Decision details

Vehicle and Plant Replacement Programme 2022/23 – 2023/24

Decision Maker: Cabinet

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

To consider an updated Vehicle and Plant Replacement Programme for 2022/23 and a proposed programme for 2023/24

Decisions:

RESOLVED:

 

1.     That the Cabinet recommend that Council approve a 2023/24 Vehicles and Plant Replacement budget of £2.400 million, to accommodate the purchases originally intended to be made in 2022/23, whilst noting the revenue implications to be picked up within the Council’s Medium Term Financial Plan.

 

2.     That the Cabinet note the intention to present the broader replacement programme 2023/24 as part of the Council’s Medium Term Financial Planning.

 

REASONS FOR DECISION:

 

As set out in the report.

 

KEY DECISION:

 

Report to Cabinet and Full Council.

 

PORTFOLIO:

 

Environment and Coastal Services / Finance, Investment and Corporate Services.

 

ALTERNATIVE OPTIONS CONSIDERED/REJECTED:

 

As set out in the report.

 

DECLARATIONS OF INTEREST(S):

 

None.

 

DISCUSSION:

 

The Portfolio Holder introduced the report and commended the recommendations.

 

The Service Manager, Waste and Transport, highlighted the challenges faced by the service in undertaking the replacement programme.  Detailed in full in the report, supply chain issues, inflation and global pressures were all contributing to the complexity of delivering the programme.  The table at 4.2 of the report detailed the current lead in times, which were significantly lengthened since 2019.  The Council’s commitment to contributing positively to tackle the Climate and Nature Emergency was highlighted, particularly in exploring alternative fuel options.

 

In response to one Member’s question on the cost of keeping older vehicles on the road, it was noted that there was an existing vehicle maintenance budget.  However, the economic life of Council vehicles and plant were continually reviewed to ensure the appropriate condition and reliability.

 

 

Reason Key: Expenditure > £50,000;

Other reasons / organisations consulted

N/A

Consultees

Executive Management Team and relevant Portfolio Holders

Contact: Alan Bethune, Strategic Director of Corporate Resources & Transformation, Section 151 Officer Email: alan.bethune@nfdc.gov.uk, Chris Noble, Assistant Director Place Operations Email: chris.noble@nfdc.gov.uk.

Report author: Alan Bethune

Publication date: 20/09/2022

Date of decision: 07/09/2022

Decided at meeting: 07/09/2022 - Cabinet

Accompanying Documents: